Supply, Repair, Installation and Maintenance of Sewer Depth and Event Duration Monitors
In plain English
The notice doesn't say
The notice as published
We need c15,000 - 30,000 additional Sewer Depth Monitors and c900 Event Duration Monitors (installation & spares) to be installed by the end of AMP8. This number of SDM installations was calculated in the strategic modelling of blockage, flooding and pollution performance and is part of a suite of planned interventions (including sewer cleaning, customer education, sewer rehabilitation) that are identified to deliver performance improvements through AMP8. This procurement is to source service provides for the supply/repair of devices and service providers for the installation and maintenance. It will be split into 5 lots: •Lot 1a Supply/repair of Sewer Depth Monitors (Trunk) •Lot 1b Supply/repair of Sewer Depth Monitors (Network) •Lot 2 Supply/repair of Event Duration Monitors •Lot 3 Installation and maintenance of Sewer Depth Monitors •Lot 4 Installation and maintenance of Event Duration Monitors