TVCA-PROC-0785 - Redcar Central Station Early Contractor Involvement (ECI)
In plain English
The notice doesn't say
The notice as published
Tees Valley Combined Authority (TVCA) (the ‘Contacting Authority’), part of the Tees Valley Combined Authority Group, has awarded a contract for Redcar Central Station Early Contractor Involvement (ECI), to undertake gap analysis / review on current ES2 documentation produced, and advise and complete ES3 surveys, risks review, constructability and feasibility on option selection. For transparency, the contract start date was 22nd July 2026, however there has been a delay with signing due to resource. The contract was signed on 22nd July 2026.