Market Engagement - Removal of Spring Hangers - Hinkley Point A
In plain English
The notice doesn't say
Who holds it now
Last won by Aureos Highways Limited in Nov 2026.
- Dungeness Site boiler & ancillary equipment removalAureos Highways Limited
- Dungeness Boilers Principal DesignerC & D Demolition Consultants Limited £1.4m
- DCP Stores Extension - Engineering Support RequirementAtkinsréalis UK Limited, Amentum Clean Energy Limited, Cavendish Nuclear £150k
What you're up against
- The last two awards went to different firms: this buyer has changed supplier before.
- 5 different firms won this buyer's 3 awards for this kind of work in 2026.
The notice as published
Nuclear Restoration Services (NRS) is undertaking preliminary market engagement to inform a potential future procurement for the design and delivery of works to remove spring hanger assemblies associated with Reactor 1 and Reactor 2 at Hinkley Point A. The anticipated scope includes the design and installation of temporary supports, de-energisation of springs, removal of spring hanger assemblies in their entirety, and removal of temporary works. NRS is seeking feedback from the market on the proposed scope, delivery approach, capability requirements, programme considerations and commercial arrangements.