Kestrel

Dearne Fire Station Chiller Replacement

South Yorkshire Fire and Rescue Authority · published Wed 18 Nov 2026

In plain English

Reading the notice and writing a summary. This takes a few seconds the first time.

The documents are on In-Tend, where the bid is sent too. It's free to register there.

The notice as published

The project comprises the complete design verification, supply, installation, testing, commissioning and handover of a new permanent air-cooled chiller system serving Dearne Community Fire Station located at S63 5DN. The works are to provide reliable cooling provision to the existing building systems following a prolonged history of underperformance and failure of the legacy heating/cooling plant. The new installation shall be designed, installed and commissioned as a complete operational system, subject to a detailed contractor site survey and independent validation of the actual cooling loads and existing system condition. The contract works are to take place January 2027 (date by mutual agreement with the contract manager.)