Kestrel

DfI Rivers Directorate T-1163 Inspection and Maintenance of Underground Infrastructure Framework

DfI Transport and Road Asset Management (TRAM) · published Fri 20 Nov 2026

In plain English

Reading the notice and writing a summary. This takes a few seconds the first time.

Who holds it now

Last won by John Mcquillan (Contracts) Limited in Sep 2026, for £5.2m.

What you're up against

  • The last two awards went to different firms: this buyer has changed supplier before.
  • 3 different firms won this buyer's 3 awards for this kind of work in 2026.
  • It last went for £5.2m in 2026.

From DfI Transport and Road Asset Management (TRAM)'s earlier award notices for the same kind of work. The tender documents usually say which contract this one replaces.

The documents are on eTendersNI, where the bid is sent too. It's free to register there.

The notice as published

The Department for Infrastructure Inspection and Maintenance of Underground Infrastructure Framework will include the following work activities: A) Desilting of Culverts B) CCTV and Fly-through Surveys of Culverts C) Trenchless / Specialist Repairs of Culverts D) Traffic Management, Gaining Access to Culverts, Associated Civil Works E) Small Scale Civil Works F) Underground Man Entry Repairs The Framework will comprise of three area Lots (Works Orders valued up to £300k) covering the following areas: IMUF 1 - Greater Belfast; IMUF 2 - Coleraine, Omagh and Fermanagh; IMUF 3 - Armagh and Lisburn. Please note: For this procurement, Suppliers submissions are required to be uploaded via the eTendersNI CfT under Lot 1: IMUF 1 (Greater Belfast Area). This will serve as the central submission point for all Lots. Suppliers should submit their responses for every Lot they are tendering for within this single location. ICC Measured Term Contract for works within the Greater Belfast Area (Works Orders valued up to £300k). The proposed contract relates to works with a cumulative value of £2.6m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £3.25m (ex VAT). ICC Measured Term Contract for works within the Armagh and Lisburn Areas (Works Orders valued up to £300k). The proposed contract relates to works with a cumulative value of £1.56m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £1.95m (ex VAT). ICC Measured Term Contract for works within the Coleraine, Omagh and Fermanagh Areas (Works Orders valued up to £300k). The proposed contract relates to works with a cumulative value of £1.5m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £1.5m (ex VAT).