Project L& Pentland Peatland Restoration Project
In plain English
The notice doesn't say
The notice as published
Peatland restoration of an upland blanket bog using low-ground-pressure excavators and ATVs. Upland blanket bog restoration over 12 subsites totalling 420.54 ha of peatland restoration over 2 years. Delivery expected in two phases between September 2027 - February 2028 and September 2028 - February 2029. Upland blanket bog restoration over 2 subsites totalling 165.69 ha of peatland restoration between September 2027 - February 2028. Upland blanket bog restoration over 1 site totalling 135.4 ha of peatland restoration. Delivery expected between February 2028 and September 2029 - February 2030. Upland blanket bog restoration over 2 subsites totalling 263.21 ha of peatland restoration. Delivery is expected between September 2028 - February 2029.