  • The buyer, BIP Solutions Limited, wants a supplier to design, supply, install, test and commission four UPS (uninterruptible power supply) systems at three sites: Stoneleigh, Canley Brook and Burton Green.
  • Each unit is a 210 kVA system with complete VRLA battery packs giving 90 minutes' backup, plus isolation transformers, changeover and bypass equipment, building management system interfaces, and full testing and handover documentation.
  • Some design details, such as the Canley Brook design load, are still to be confirmed before manufacture.

The notice doesn't say

  • How long the contract runs
  • Whether staff transfer to you (TUPE)
  • How bids are scored
  • Whether it suits small firms

These are usually in the tender documents.

The documents are on competefor.co.uk, where the bid is sent too. It's free to register there.

The notice as published

The Subcontractor shall design, manufacture, supply, deliver, test and commission 4 No. complete UPS systems: 1 No. at Stoneleigh, 1 No. at Canley Brook and 2 No. at Burton Green. 1. Technical Requirements Each UPS shall be rated at 210 kVA, 400 V, with 4 x 60 kW power modules and N+1 hot-swappable architecture. The Subcontractor shall demonstrate that the required connected load remains supported with one power module unavailable. Requirement Stoneleigh Canley Brook Burton Green Battery sizing load 35 kW 17 kW 70 kW Connected design load 31 kW TBC 66 kW Protection breaker 100 A 100 A 250 A Separate static switch N/A N/A 400 A, 400 V Each UPS shall provide an output fault current of 987 A for 200 ms. Supplier submissions shall demonstrate compatibility with the project protection requirements. 2. Batteries Provide complete VRLA battery systems, including racks/enclosures, interconnections, isolation and protection, delivering 90 minutes' autonomy at the specified battery sizing load. Batteries shall recharge to 95% within 900 minutes. Submit sizing and recharge calculations. 3. Transformers and Ancillary Equipment Provide 250 kVA, 1:1, Dzn0 input and output isolation transformers, together with ATS, static switching and external maintenance bypass arrangements required by the approved site-specific drawings. ATS shall be 400 A, four-pole where indicated. Include all interconnecting cables, battery cables, protective devices and terminations identified as the UPS supplier's responsibility. Coordinate interfaces with incoming supplies and UPS switchboards. 4. Monitoring Provide BMS interfaces for battery DC voltage, charge percentage, battery alarms/faults and charger status/alarms. Include communications protocols, interface hardware and point schedules for the UPS, ATS and UPS switchboard, with interface testing. 5. Delivery and Coordination Scheduled UPS cabinet dimensions are 1,200 W x 1,996 H x 1,100 D mm. Confirm complete equipment footprints, weights, clearances and delivery requirements before manufacture. 6. Testing and Handover Include FAT, commissioning, SAT and resistive load bank testing, with all temporary equipment, connections and removal. Demonstrate capacity, autonomy, recharge, redundancy, transfer/bypass operation, alarms and communications. Provide evidence of fault-current performance. Submit equipment drawings, schematics, protection data, test procedures/results, commissioning records, as-built information and O&M manuals. Suppliers shall identify proposed equipment and deviations. Confirm the missing Canley Brook design load, whether Burton Green loads apply per UPS, and site-specific equipment quantities and supply boundaries before manufacture. Additional information: Please review attached schematic and narrative specification.