Kestrel

The Design & Replacement of the Offices Chiller Plant and Associated Works at Bristol & Bath Science Park – Emersons Green.

South Gloucestershire Council · published Fri 27 Nov 2026

In plain English

Reading the notice and writing a summary. This takes a few seconds the first time.

Who holds it now

Last won by Airmec Essential Services in Feb 2025, for £74k.

Award notice: The Control of Legionella Bacteria in Hot and Cold Water Systems in Accordance with HSE Approved Code of Practice L8 & HSG 274 - 2024-2027

What you're up against

  • It last went for £74k in 2025.

From South Gloucestershire Council's earlier award notices for the same kind of work. The tender documents usually say which contract this one replaces.

The documents are on ProContract, where the bid is sent too. It's free to register there.

The notice as published

The Council intends to appoint a suitably qualified Mechanical and Electrical Contractor to act as Principal Contractor for the design, supply, installation, testing, and commissioning of replacement office chiller plant with associated mechanical, electrical and building works at The Bristol & Bath Science Park, Emersons Green. The works are programmed for delivery during 2027, with all works to be completed and the installation fully operational by 25 June 2027. The Council commissioned an engineering consultant to undertake an assessment of the existing office chiller plant to verify that its installed capacity remains appropriate for the building's cooling demand. The assessment concluded that the existing chillers are adequately sized, and consequently the replacement chillers will be designed and selected to provide an equivalent cooling duty and performance. The appointed Contractor shall be required to demonstrate a proven track record in delivering projects of a similar nature, scale, value, and programme, together with the organisational capacity and financial resilience necessary to fulfil the Contract. The Council will not accept proposals whereby the entirety of the works is subcontracted. The Principal Contractor must maintain direct control over the delivery of the principal work packages and remain fully responsible for the effective management, coordination, and performance of all specialist subcontractors engaged in the execution of the works.